Procurement float for a long-lead item is best described as:
Correct Answer
C) The time cushion between planned delivery and the date the item is actually needed for installation
Procurement float is schedule cushion between expected delivery and the required installation or on-site date. Other choices are unrelated to procurement schedule risk.
Why This Is the Correct Answer
Procurement float is schedule cushion between expected delivery and the required installation or on-site date. Other choices are unrelated to procurement schedule risk.
Why the Other Options Are Wrong
Option A: Measure the time between supplier invoice date and final payment, leaving procurement float unverified
The trap in A is The supplier's logo color. That selection is wrong because the choice would not get the project to The time cushion between planned delivery and the date the item is actually needed for installation, which is the Procurement float result verified by the source; Procurement float is the time cushion between planned delivery and required use.
Option B: Measure the bond amount held until the item is delivered
Choice B gives The bond amount stated on bid day. Its specific error: it names a financial document or payment mechanism, not the Procurement float action/result stated by The time cushion between planned delivery and the date the item is actually needed for installation.
Option D: Measure the retainage percentage applied to stored materials
In procurement and contracting, The retainage percentage on stored materials is the wrong selection for Procurement float: it shifts the question into contract administration money flow.
Memory Technique
Picture procurement float doing the job; the answer names that job as The time cushion between planned delivery and the date the item is actually needed for installation.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Procurement float concept" to confirm that Procurement float is schedule cushion between expected delivery and the required installation or on-site date.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
