Before backfill begins, what is the purpose of a subcontract flow-down clause?
Correct Answer
A) Pass applicable prime-contract obligations to the subcontractor for its work
Pass applicable prime-contract obligations to the subcontractor for its work is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 103.
Why This Is the Correct Answer
Pass applicable prime-contract obligations to the subcontractor for its work is the controlling requirement
Why the Other Options Are Wrong
Option B: Release the owner from all payment duties, leaving subcontract flow-down unverified
In procurement and contracting, Release the owner from all payment duties is the wrong selection for Subcontract flow-down: the option answers a paperwork, payment, or bonding issue.
Option C: The contractor should delete the drawings
The trap in C is Delete the drawings. That selection is wrong because it removes the controlling Subcontract flow-down requirement instead of meeting it.
Option D: The contractor should replace insurance certificates
Choice D gives Replace insurance certificates. Its specific error: it treats Subcontract flow-down as optional.
Memory Technique
Make subcontract flow-down a tabbed card: cite the exact condition, then choose Pass applicable prime-contract obligations to the subcontractor for its work.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Flow-down provisions" to confirm that Pass applicable prime-contract obligations to the subcontractor for its work is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass