What is a key limitation when using a trench shield?
Correct Answer
C) Workers must stay within the shielded area and the shield must be used according to its tabulated data.
Trench shields protect only when used according to manufacturer/tabulated data and workers remain within the protected zone.
Why This Is the Correct Answer
Trench shields protect only when used according to manufacturer/tabulated data and workers remain within the protected zone.
Why the Other Options Are Wrong
Option A: The shield allows spoil at the edge
In site construction, The shield allows spoil at the edge is the wrong selection for Trench shield use: it answers the Trench shield use prompt with the wrong practical move.
Option B: Base the trench shield use response on the shield eliminates egress requirements
The trap in B is The shield eliminates egress requirements. That selection is wrong because it removes the controlling Trench shield use requirement instead of meeting it.
Option D: The shield can be lifted with workers inside, leaving trench shield use unverified
Choice D (The shield can be lifted with workers inside) is rejected because the option does not produce the required Trench shield use outcome, Workers must stay within the shielded area and the shield must be used according to its tabulated data.
Memory Technique
Treat trench shield use like a labeled shelf; only the matching condition belongs with Workers must stay within the shielded area and the shield must be used according to its tabulated data.
Reference Hint
Open OSHA 29 CFR 1926 Subpart P; EPA Construction General Permit concepts where applicable; use OSHA 1926 Subpart P protective systems to confirm that Trench shields protect only when used according to manufacturer/tabulated data and workers remain within the protected zone.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass