A major structural addendum is issued a few hours before bids are due, and several bidders cannot obtain subcontractor pricing. What procurement action best protects fair competition?
Correct Answer
C) Extend the bid date or otherwise give bidders adequate time to price the addendum
A major late addendum may require extending the bid date so all bidders can price the same documents. Other choices create unequal bidding or convert pre-bid scope into disputed free work.
Why This Is the Correct Answer
A major late addendum may require extending the bid date so all bidders can price the same documents. Other choices create unequal bidding or convert pre-bid scope into disputed free work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A rectangular lite is 42 in. wide and 78 in. high. Glazing stop is needed around all four sides, and the cut list adds 10 percent waste. What stop length should be carried?
Next Question
A critical equipment submittal is two weeks late and fabrication cannot start. What should be escalated?