A major structural addendum is issued a few hours before bids are due, and several bidders cannot obtain subcontractor pricing. What procurement action best protects fair competition?
Correct Answer
C) Extend the bid date or otherwise give bidders adequate time to price the addendum
A major late addendum may require extending the bid date so all bidders can price the same documents. Other choices create unequal bidding or convert pre-bid scope into disputed free work.
Why This Is the Correct Answer
A major late addendum may require extending the bid date so all bidders can price the same documents. Other choices create unequal bidding or convert pre-bid scope into disputed free work.
Why the Other Options Are Wrong
Option A: Award immediately and treat the addendum as free work
Choice A gives Award immediately and treat the addendum as free work. Its specific error: the option does not produce the required Late addendum outcome, Extend the bid date or otherwise give bidders adequate time to price the addendum.
Option B: Tell only one bidder to ignore the addendum and leave late addendum unchecked
Choice B (Tell only one bidder to ignore the addendum) is rejected because it tries to bypass the Late addendum checkpoint.
Option D: The bidder should open bids and negotiate privately with the favorite bidder
The trap in D is Open bids and negotiate privately with the favorite bidder. That selection is wrong because the option answers a paperwork, payment, or bonding issue.
Memory Technique
Pair late addendum with the real field trigger, then choose the response that produces Extend the bid date or otherwise give bidders adequate time to price the addendum.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - addenda / bid form acknowledgment to confirm that A major late addendum may require extending the bid date so all bidders can price the same documents.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A rectangular lite is 42 in. wide and 78 in. high. Glazing stop is needed around all four sides, and the cut list adds 10 percent waste. What stop length should be carried?
Next Question
A critical equipment submittal is two weeks late and fabrication cannot start. What should be escalated?