A custom pump is required on site by day 110. Review takes 14 days, fabrication takes 42 days, and shipping takes 6 days after release. What is the latest day the submittal can be issued for review?
Correct Answer
A) Day 48
Total procurement duration from submittal issue is 14 + 42 + 6 = 62 days. Latest submittal issue is day 110 - 62 = day 48. Other choices omit one procurement step or subtract the wrong duration.
Why This Is the Correct Answer
Total procurement duration from submittal issue is 14 + 42 + 6 = 62 days. Latest submittal issue is day 110 - 62 = day 48. Other choices omit one procurement step or subtract the wrong duration.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A hydronic piping scope has 28 straight pipe pieces, each 20 ft long. The insulation order includes 5 percent for cuts and fittings. What insulation length should be carried?
Next Question
Stored ceiling tile pallets are placed directly in front of a switchgear lineup on the day of startup. What should the superintendent require before energization work proceeds?