NASCLAProcurement and Contracting Requirementsmedium

A custom pump is required on site by day 110. Review takes 14 days, fabrication takes 42 days, and shipping takes 6 days after release. What is the latest day the submittal can be issued for review?

Correct Answer

A) Day 48

Total procurement duration from submittal issue is 14 + 42 + 6 = 62 days. Latest submittal issue is day 110 - 62 = day 48. Other choices omit one procurement step or subtract the wrong duration.

Answer Options
A
Day 48
B
Day 54
C
Day 62
D
Day 68

Why This Is the Correct Answer

Total procurement duration from submittal issue is 14 + 42 + 6 = 62 days. Latest submittal issue is day 110 - 62 = day 48. Other choices omit one procurement step or subtract the wrong duration.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.