A custom pump is required on site by day 110. Review takes 14 days, fabrication takes 42 days, and shipping takes 6 days after release. What is the latest day the submittal can be issued for review?
Correct Answer
A) Day 48
Total procurement duration from submittal issue is 14 + 42 + 6 = 62 days. Latest submittal issue is day 110 - 62 = day 48. Other choices omit one procurement step or subtract the wrong duration.
Why This Is the Correct Answer
Total procurement duration from submittal issue is 14 + 42 + 6 = 62 days. Latest submittal issue is day 110 - 62 = day 48. Other choices omit one procurement step or subtract the wrong duration.
Why the Other Options Are Wrong
Option B: Day 54
submittal due date, choice b: Day 54 is off by 6 from the checked result Day 48 because it misuses the 6-day item (shipping takes 6 days after release).
Option C: Day 62
submittal due date, choice c: Day 62 stops at the intermediate Day 62 instead of carrying the remaining calculation step through to Day 48.
Option D: Day 68
submittal due date, choice d: Day 68 equals 110 - 42. That subtracts those two listed numbers in that order.
Memory Technique
Store submittal due date with its last math move; nearby answers are usually unfinished versions of Day 48.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Procurement schedule calculation" to confirm that Total procurement duration from submittal issue is 14 + 42 + 6 = 62 days.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A hydronic piping scope has 28 straight pipe pieces, each 20 ft long. The insulation order includes 5 percent for cuts and fittings. What insulation length should be carried?
Next Question
Stored ceiling tile pallets are placed directly in front of a switchgear lineup on the day of startup. What should the superintendent require before energization work proceeds?