A steel stair shop drawing is marked reviewed. What should the contractor understand about that review?
Correct Answer
D) It does not relieve the contractor from responsibility for compliance with the contract documents
Shop drawing review does not relieve the contractor of responsibility for compliance, dimensions, coordination, and contract requirements. Other choices overstate the legal effect of review.
Why This Is the Correct Answer
Shop drawing review does not relieve the contractor of responsibility for compliance, dimensions, coordination, and contract requirements. Other choices overstate the legal effect of review.
Why the Other Options Are Wrong
Option A: Use shop drawing review to change the contract price automatically
In procurement and contracting, It changes the contract price automatically is the wrong selection for Shop drawing review: it points to It changes the contract price automatically, but.
Option B: Use shop drawing review to delete code requirements from the work
The trap in B is It deletes code requirements from the work. That selection is wrong because the option tries to substitute, waive, or delete the Shop drawing review control; the item instead requires It does not relieve the contractor from responsibility for compliance with the contract documents.
Option C: Use shop drawing review to transfer all field dimension responsibility to the reviewer
Choice C gives It transfers all field dimension responsibility to the reviewer. Its specific error: it leaves out the controlling Shop drawing review result: It does not relieve the contractor from responsibility for compliance with the contract documents.
Memory Technique
Link shop drawing review to its book condition; a different condition means a different answer than It does not relieve the contractor from responsibility for compliance with the contract documents.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Submittal and shop drawing review" to confirm that Shop drawing review does not relieve the contractor of responsibility for compliance, dimensions, coordination, and contract requirements.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass