A steel stair shop drawing is marked reviewed. What should the contractor understand about that review?

Correct Answer

D) It does not relieve the contractor from responsibility for compliance with the contract documents

Shop drawing review does not relieve the contractor of responsibility for compliance, dimensions, coordination, and contract requirements. Other choices overstate the legal effect of review.

Answer Options
A
Use shop drawing review to change the contract price automatically
B
Use shop drawing review to delete code requirements from the work
C
Use shop drawing review to transfer all field dimension responsibility to the reviewer
D
It does not relieve the contractor from responsibility for compliance with the contract documents

Why This Is the Correct Answer

Shop drawing review does not relieve the contractor of responsibility for compliance, dimensions, coordination, and contract requirements. Other choices overstate the legal effect of review.

Why the Other Options Are Wrong

Option A: Use shop drawing review to change the contract price automatically

In procurement and contracting, It changes the contract price automatically is the wrong selection for Shop drawing review: it points to It changes the contract price automatically, but.

Option B: Use shop drawing review to delete code requirements from the work

The trap in B is It deletes code requirements from the work. That selection is wrong because the option tries to substitute, waive, or delete the Shop drawing review control; the item instead requires It does not relieve the contractor from responsibility for compliance with the contract documents.

Option C: Use shop drawing review to transfer all field dimension responsibility to the reviewer

Choice C gives It transfers all field dimension responsibility to the reviewer. Its specific error: it leaves out the controlling Shop drawing review result: It does not relieve the contractor from responsibility for compliance with the contract documents.

Memory Technique

Link shop drawing review to its book condition; a different condition means a different answer than It does not relieve the contractor from responsibility for compliance with the contract documents.

Reference Hint

Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Submittal and shop drawing review" to confirm that Shop drawing review does not relieve the contractor of responsibility for compliance, dimensions, coordination, and contract requirements.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.