Why are weep openings placed above flashing in brick veneer?
Correct Answer
D) To drain water from the veneer cavity to the exterior
Weeps provide a path for water collected by flashing to drain from the veneer cavity to the exterior. Other choices do not describe the drainage function of weeps.
Why This Is the Correct Answer
Weeps provide a path for water collected by flashing to drain from the veneer cavity to the exterior. Other choices do not describe the drainage function of weeps.
Why the Other Options Are Wrong
Option A: Use weeps to let masons see the backup wall, leaving weeps unverified
In masonry work, To let masons see the backup wall is the wrong selection for Weeps: it answers the Weeps prompt with the wrong practical move.
Option B: Use weeps to reduce the number of veneer anchors
The trap in B is To reduce the number of veneer anchors. That selection is wrong because it leaves out the controlling Weeps result: To drain water.
Option C: Use weeps to increase mortar strength at the shelf angle
Choice C gives To increase mortar strength at the shelf angle. Its specific error: the choice would not get the project to To drain water from the veneer cavity to the exterior, which is the Weeps result verified by the source.
Memory Technique
Picture weeps doing the job; the answer names that job as To drain water from the veneer cavity to the exterior.
Reference Hint
Open International Building Code 2021 or 2024; use the index entry or section for "Masonry veneer flashing and weep function" to confirm that Weeps provide a path for water collected by flashing to drain from the veneer cavity to the exterior.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Fresh concrete drops too far through congested reinforcing and the coarse aggregate collects at the bottom while paste flows ahead. Which defect is occurring?
Next Question
A negotiated project reimburses the contractor for allowable costs and pays a separately stated fee. Which contract type is being described?
