Fresh concrete drops too far through congested reinforcing and the coarse aggregate collects at the bottom while paste flows ahead. Which defect is occurring?
Correct Answer
B) Segregation
Segregation is separation of coarse aggregate from mortar or paste, often from mishandling, excess slump, or improper placement. Other choices: bleeding is upward water migration, alkali-silica reaction is a hardened concrete durability reaction, and carbonation is a chemical process involving carbon dioxide.
Why This Is the Correct Answer
Segregation is separation of coarse aggregate from mortar or paste, often from mishandling, excess slump, or improper placement.
Why the Other Options Are Wrong
Option A: Bleeding only
In concrete work, Bleeding only is the wrong selection for Segregation: the action skips the timing, documentation, or field-control step needed for Segregation.
Option C: Alkali-silica reaction
Choice C gives Alkali-silica reaction. Its specific error: it leaves out the controlling Segregation result: Segregation.
Option D: Carbonation
Choice D (Carbonation) is rejected because the choice would not get the project to Segregation, which is the Segregation result verified by the source. The cited answer is Segregation.
Memory Technique
Make segregation a purpose cue; if the choice changes the purpose, it cannot be Segregation.
Reference Hint
Open The Contractor's Guide to Quality Concrete Construction, 4th Ed., 2018; use the index entry or section for "Fresh concrete handling and segregation" to confirm that Segregation is separation of coarse aggregate from mortar or paste, often from mishandling, excess slump, or improper placement.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass