A negotiated project reimburses the contractor for allowable costs and pays a separately stated fee. Which contract type is being described?
Correct Answer
B) Cost-plus contract
A cost-plus contract reimburses allowable project costs and adds the agreed fee. Other choices describe measured-unit pricing, bid security, or an alternate bid item.
Why This Is the Correct Answer
A cost-plus contract reimburses allowable project costs and adds the agreed fee. Other choices describe measured-unit pricing, bid security, or an alternate bid item.
Why the Other Options Are Wrong
Option A: Unit-price contract
Choice A gives Unit-price contract. Its specific error: the option does not produce the required Cost-plus contract outcome, Cost-plus contract.
Option C: Bid bond
In procurement and contracting, Bid bond is the wrong selection for Cost-plus contract: it names a financial document or payment mechanism, not the Cost-plus contract action/result stated by Cost-plus contract.
Option D: Deductive alternate
The trap in D is Deductive alternate. That selection is wrong because it leaves out the controlling Cost-plus contract result: Cost-plus contract.
Memory Technique
Make cost-plus contract a tabbed card: cite the exact condition, then choose Cost-plus contract.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Contract types - cost plus" to confirm that A cost-plus contract reimburses allowable project costs and adds the agreed fee.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass