What is the contractor's usual coordination responsibility for required permit inspections?

Correct Answer

D) Schedule inspections before covering or proceeding past work that must be observed.

Permit inspections must be coordinated before work is concealed or advanced beyond an inspection point.

Answer Options
A
Make assume inspections happen automatically the answer for permit inspection coordination
B
Cover work first to protect it from weather
C
Ask the supplier to waive the inspection, leaving permit inspection coordination unverified
D
Schedule inspections before covering or proceeding past work that must be observed.

Why This Is the Correct Answer

Permit inspections must be coordinated before work is concealed or advanced beyond an inspection point.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.