Concrete testing is required but the testing agency was not notified. What should be improved?

Correct Answer

C) Inspection/testing notice procedures tied to the work schedule.

Testing agencies must be coordinated with scheduled work so required observations and samples occur.

Answer Options
A
Improve the bid-bond amount listed in the procurement file
B
Improve the color coding of field-office signs
C
Inspection/testing notice procedures tied to the work schedule.
D
Apply improve the final-cleaning checklist date to the testing agency notice condition

Why This Is the Correct Answer

Testing agencies must be coordinated with scheduled work so required observations and samples occur.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.