An inspector gives verbal direction that differs from the drawings. What should the contractor do?

Correct Answer

C) Document the direction and seek written clarification before relying on it for a contract change.

Verbal field comments should be documented and clarified in writing before contract reliance.

Answer Options
A
Treat the verbal comment as a signed change order
B
The contractor should ignore all inspections
C
Document the direction and seek written clarification before relying on it for a contract change.
D
The contractor should remove the drawing from the record set

Why This Is the Correct Answer

Verbal field comments should be documented and clarified in writing before contract reliance.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.