A late air handler threatens startup. What information belongs in the expediting log?
Correct Answer
C) Submittal status, release date, fabrication status, ship date, delivery constraints, and responsible contact.
Expediting tracks the information needed to recover long-lead deliveries.
Why This Is the Correct Answer
Expediting tracks the information needed to recover long-lead deliveries.
Why the Other Options Are Wrong
Option A: Use the worker orientation roster as the expediting log
In general project requirements, Only the worker orientation roster. is the wrong selection for Procurement expediting log: it leaves the work at an informal or incomplete stage, while Procurement expediting log requires Submittal status, release date, fabrication status, ship date, delivery constraints, and.
Option B: Let the late air handler proceed without updating release or ship dates
The trap in B is Only the final punch list. That selection is wrong because the option delays or omits the controlling step.
Option D: Record only the permit number in the expediting log
Choice D (Only the permit number.) is rejected because it tries to bypass the Procurement expediting log checkpoint.
Memory Technique
Remember procurement expediting log by its jobsite consequence: the correct move points to Submittal status, release date, fabrication status, ship date, delivery constraints, and responsible contact.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Expediting tracks the information needed to recover long-lead deliveries.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass