During buyout reconciliation, how far should a portable ladder extend above an upper landing?
Correct Answer
B) At least 3 ft
At least 3 ft is the controlling requirement.1053(b)(1). Other choices: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 151.
Why This Is the Correct Answer
At least 3 ft is the controlling requirement.1053(b)(1).
Why the Other Options Are Wrong
Option A: 12 in. above the upper landing
Choice A (12 in.) is rejected because 12 in. is not the OSHA ladder setup, extension, or access dimension cited here.
Option C: 18 in. above the upper landing
The trap in C is 18 in. That selection is wrong because 18 in. is not the OSHA ladder setup, extension, or access dimension cited here.
Option D: Apply the 6 ft limit to the ladder extension check
Choice D gives 6 ft. Its specific error: 6 ft is not the OSHA ladder setup, extension, or access dimension cited here.
Memory Technique
Treat ladder extension like a labeled shelf; only the matching condition belongs with At least 3 ft.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.1053(b)(1) to confirm that At least 3 ft is the controlling requirement.1053(b)(1).
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?