NASCLAGeneral Reqmedium22% of exam part

A work package has earned value of $240,000 and planned value of $300,000. What is the SPI?

Correct Answer

C) 0.80

SPI is EV / PV = $240,000 / $300,000 = 0.80.

Answer Options
A
1.25
B
0.60
C
0.80
D
1.08

Why This Is the Correct Answer

SPI is EV / PV = $240,000 / $300,000 = 0.80.

Why the Other Options Are Wrong

Option A: 1.25

earned value spi, choice a: 1.25 equals $300,000 / $240,000. That divides those two listed numbers.

Option B: 0.60

earned value spi, choice b: 0.60 backs into 0.75 when divided by 240000 / 300000; the accepted setup gives 1 on that same base.

Option D: 1.08

earned value spi, choice d: 1.08 backs into 1.35 when divided by 240000 / 300000; the accepted setup gives 1 on that same base.

Memory Technique

Say the earned value SPI rule aloud as a chain; the chain ends at 0.80, not an intermediate stop.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - duration / float / baseline / updating / variance to confirm that SPI is EV / PV = $240,000 / $300,000 = 0.80.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.