A work package has earned value of $240,000 and planned value of $300,000. What is the SPI?
Correct Answer
C) 0.80
SPI is EV / PV = $240,000 / $300,000 = 0.80.
Why This Is the Correct Answer
SPI is EV / PV = $240,000 / $300,000 = 0.80.
Why the Other Options Are Wrong
Option A: 1.25
earned value spi, choice a: 1.25 equals $300,000 / $240,000. That divides those two listed numbers.
Option B: 0.60
earned value spi, choice b: 0.60 backs into 0.75 when divided by 240000 / 300000; the accepted setup gives 1 on that same base.
Option D: 1.08
earned value spi, choice d: 1.08 backs into 1.35 when divided by 240000 / 300000; the accepted setup gives 1 on that same base.
Memory Technique
Say the earned value SPI rule aloud as a chain; the chain ends at 0.80, not an intermediate stop.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - duration / float / baseline / updating / variance to confirm that SPI is EV / PV = $240,000 / $300,000 = 0.80.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
