A building is usable by the owner except for minor incomplete work. Which closeout milestone usually describes that condition?
Correct Answer
A) Substantial completion
Substantial completion is reached when the work, or a designated portion, is sufficiently complete for the owner to occupy or use it for its intended purpose. Other choices occur before or outside closeout.
Why This Is the Correct Answer
Substantial completion is reached when the work, or a designated portion, is sufficiently complete for the owner to occupy or use it for its intended purpose. Other choices occur before or outside closeout.
Why the Other Options Are Wrong
Option B: Notice to bidders
Choice B gives Notice to bidders. Its specific error: it shifts the question into contract administration money flow.
Option C: Bid opening
Choice C (Bid opening) is rejected because it names a financial document or payment mechanism, not the Substantial completion action/result stated by Substantial completion. The cited answer is Substantial completion.
Option D: Preconstruction conference
In procurement and contracting, Preconstruction conference is the wrong selection for Substantial completion: it points to Preconstruction conference, but.
Memory Technique
Use a release point memory cue for substantial completion: the stem's condition unlocks Substantial completion.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Substantial completion" to confirm that Substantial completion is reached when the work, or a designated portion, is sufficiently complete for the owner to occupy or use it for its intended purpose.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
