A crew will weld near stored packaging. What should be verified before work starts?

Correct Answer

C) Hot work permit, removal or shielding of combustibles, extinguisher, and fire watch requirements.

Hot work controls address ignition hazards before welding or cutting starts.

Answer Options
A
Rely on the superintendent's visual judgment as enough evidence for hot work near combustibles
B
Treat the concrete delivery ticket as the hot-work permit
C
Hot work permit, removal or shielding of combustibles, extinguisher, and fire watch requirements.
D
Use a fire watch only after sparks are visible

Why This Is the Correct Answer

Hot work controls address ignition hazards before welding or cutting starts.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.