A team closes 36 punch items in 4 workdays. What is the closure rate?

Correct Answer

C) 9 items/day

The closure rate is 36 items / 4 days = 9 items/day.

Answer Options
A
6 items/day
B
12 items/day
C
9 items/day
D
144 items/day

Why This Is the Correct Answer

The closure rate is 36 items / 4 days = 9 items/day.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.