NASCLAGeneral Requirementsmedium

Installed finish work does not match the accepted mockup. What should the project manager require?

Correct Answer

C) Compare the work to the mockup, document the nonconformance, and correct or obtain approved disposition.

The accepted mockup is the benchmark. Deviations require correction or approved disposition.

Answer Options
A
Change the mockup to match the deficient work
B
Apply release final payment immediately to the mockup mismatch condition
C
Compare the work to the mockup, document the nonconformance, and correct or obtain approved disposition.
D
The project manager should delete the finish specification

Why This Is the Correct Answer

The accepted mockup is the benchmark. Deviations require correction or approved disposition.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.