A footing inspection is required before concrete placement, but the inspector has not arrived. What is the safest administrative action?

Correct Answer

C) Do not place concrete until the required inspection is completed or released by the authority.

Required jurisdictional inspections must occur before the covered work proceeds unless the authority releases the hold.

Answer Options
A
Place concrete and ask for retroactive approval
B
Limit permit inspection hold to cancel the permit
C
Do not place concrete until the required inspection is completed or released by the authority.
D
The project manager should use a delivery ticket as the inspection record

Why This Is the Correct Answer

Required jurisdictional inspections must occur before the covered work proceeds unless the authority releases the hold.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.