For the owner coordination call, a project records 3 recordable cases over 105,000 work hours. Using the 200,000-hour multiplier, what incident rate is closest?

Correct Answer

D) 5.7

The calculation gives 5.7 for the stated incident rate. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 221.

Answer Options
A
5.7 (unadjusted)
B
5
C
6
D
5.7

Why This Is the Correct Answer

The calculation gives 5.7 for the stated incident rate. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 221.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.