The drywall lead verifies a control-joint layout: at what excavation depth is a protective system generally required unless an exception applies?

Correct Answer

B) 5 ft or deeper

5 ft or deeper is the controlling requirement.652(a)(1). Other choices: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 144.

Answer Options
A
Set the excavation protection threshold at 3 ft
B
5 ft or deeper
C
Treat 8 ft as the controlling excavation protection result
D
Apply 20 ft to the excavation protection condition

Why This Is the Correct Answer

5 ft or deeper is the controlling requirement.652(a)(1). Other choices: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 144.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.