A crew uses the common quality-concrete rule of thumb that contraction-joint spacing in feet should be about 24 to 30 times slab thickness in inches. For a 5 in. slab, what range results?
Correct Answer
C) 10.0 to 12.5 ft
For a 5 in. slab, 24 x 5 = 120 in. = 10.0 ft and 30 x 5 = 150 in. = 12.5 ft, so the range is 10.0 to 12.5 ft. Other choices use too small or too large a thickness multiplier.
Why This Is the Correct Answer
For a 5 in. slab, 24 x 5 = 120 in. = 10.0 ft and 30 x 5 = 150 in. = 12.5 ft, so the range is 10.0 to 12.5 ft. Other choices use too small or too large a thickness multiplier.
Why the Other Options Are Wrong
Option A: 6.0 to 7.5 ft
joint spacing, choice a: the number 6.0 to 7.5 ft comes from 30 / 5.
Option B: 8.0 to 10.0 ft
joint spacing, choice b: 8.0 to 10.0 ft omits a required add-on/subtraction; the numeric gap is 2.
Option D: 15.0 to 18.0 ft
joint spacing, choice d: 15.0 to 18.0 ft is off by 5 from the checked result 10.0 to 12.5 ft because it misuses the 5 item (thickness in inches).
Memory Technique
Keep a flashing lip beside joint spacing: if one number is skipped, the option drifts away from 10.0 to 12.5 ft.
Reference Hint
Open The Contractor's Guide to Quality Concrete Construction, 4th Ed., 2018; use the index entry or section for "Slab contraction joint spacing guidance" to confirm that For a 5 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
