Why are accurate daily reports important in project administration?
Correct Answer
D) They contemporaneously record labor, equipment, weather, deliveries, visitors, and impacts.
Daily reports create a contemporaneous project record. They support, but do not replace, formal contract approvals.
Why This Is the Correct Answer
Daily reports create a contemporaneous project record. They support, but do not replace, formal contract approvals.
Why the Other Options Are Wrong
Option A: Treat daily reports as replacing signed change orders
The trap in A is They replace signed change orders. That selection is wrong because it treats Daily report evidentiary value as optional.
Option B: Use daily reports to approve insurance coverage
Choice B gives They approve insurance coverage. Its specific error: it leaves out the controlling Daily report evidentiary value result: They contemporaneously record labor, equipment, weather, deliveries, visitors, and impacts.
Option C: Treat daily reports as optional after mobilization
Choice C (They are optional after mobilization.) is rejected because the choice would not get the project to They contemporaneously record labor, equipment, weather, deliveries, visitors, and impacts.
Memory Technique
Picture daily report evidentiary value doing the job; the answer names that job as They contemporaneously record labor, equipment, weather, deliveries, visitors, and impacts.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Daily reports create a contemporaneous project record.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A crew uses the common quality-concrete rule of thumb that contraction-joint spacing in feet should be about 24 to 30 times slab thickness in inches. For a 5 in. slab, what range results?
Next Question
During overhead rough-in, EMT runs above an accessible ceiling are visibly sagging and tied to ceiling grid wires. What should the superintendent require?