A thin weak layer of fines and water is found on a slab surface where new topping must bond. In concrete work, that surface condition is best described as what?
Correct Answer
B) Laitance
Laitance is the weak surface layer of water, cement fines, and fine aggregate that can interfere with bond. Other choices: efflorescence is salt deposit, plastic shrinkage is a cracking mechanism, and entrained air is a designed air-void system.
Why This Is the Correct Answer
Laitance is the weak surface layer of water, cement fines, and fine aggregate that can interfere with bond. Other choices: efflorescence is salt deposit, plastic shrinkage is a cracking mechanism, and entrained air is a designed air-void system.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A $28,000 allowance is bought out for $24,250. What credit is due before markup terms?
Next Question
A crew uses the common quality-concrete rule of thumb that contraction-joint spacing in feet should be about 24 to 30 times slab thickness in inches. For a 5 in. slab, what range results?
