The Hialeah crew finds this floor-opening condition: floor opening is covered with loose plywood. Which safety action is required before traffic continues?

Correct Answer

B) secure the cover

Hole covers must be secured and identified so employees are protected from falling through openings.

Answer Options
A
paint it to be visible
B
secure the cover
C
workers step around it
D
add a loose sheet on top

Why This Is the Correct Answer

Hole covers must be secured and identified so employees are protected from falling through openings.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.