While preparing the subcontractor quantity check for the maintenance-shop wash bay, the one-sided curb line requires 336 LF of curb forms at 2.5 ft high on 1 side. What contact area is required?

Correct Answer

B) 840 SF

Form contact area equals length times height times the number of formed sides.

Answer Options
A
336 SF
B
840 SF
C
1,050 SF
D
841 SF

Why This Is the Correct Answer

Form contact area equals length times height times the number of formed sides.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.