The construction team is coordinating a method decision because bonded pad needs surface preparation. Which equipment pad method is best?

Correct Answer

D) roughen and clean slab before bonded pad

roughen and clean slab before bonded pad best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Answer Options
A
cast pad over dust and curing residue
B
set anchor bolts after equipment is placed
C
use sealant as pad leveling compound
D
roughen and clean slab before bonded pad

Why This Is the Correct Answer

roughen and clean slab before bonded pad best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.