Before releasing the work, the team identifies this condition: the controlling field constraint is that joint must resist water passage through concrete. Which waterstop material fits best?
Correct Answer
A) Select specified PVC or hydrophilic waterstop
specified PVC or hydrophilic waterstop best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
specified PVC or hydrophilic waterstop best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option B: Select surface sealant only at cold joint
Select surface sealant only at cold joint addresses a neighboring field issue, but not the condition or method control required for waterstop selection.
Option C: Select backer rod in construction joint
Select backer rod in construction joint addresses a neighboring field issue, but not the condition or method control required for waterstop selection.
Option D: Select roof flashing membrane in footing joint
Select roof flashing membrane in footing joint addresses a neighboring field issue, but not the condition or method control required for waterstop selection.
Memory Technique
Waterstop Selection method for Manager Checking: condition first, tool second.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Concrete water-control materials; waterstop at joints; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass