For the look-ahead planning meeting at the storm-shelter entry vestibule, the #3 stirrup stock takeoff has 60 bars at 30 ft each. Using 0.376 lb per ft for stirrup fabrication, what reinforcing weight is estimated?
Correct Answer
D) 677 lb
Reinforcing weight equals bar count times length times pounds per foot.
Why This Is the Correct Answer
Reinforcing weight equals bar count times length times pounds per foot.
Why the Other Options Are Wrong
Option A: 1,800 lb
1,800 lb is above the supported result for #3 stirrup stock; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option B: 23 lb
23 lb is below the supported result for #3 stirrup stock; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 758 lb
758 lb is above the supported result for #3 stirrup stock; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Measure to reinforcing, adjust for weight, then let Concrete Estimator set the finish line.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Reinforcing steel; stirrup stock weight; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Before the inspection hold point, the team confirms that the project condition shows that granular backfill is in a narrow trench. Which compaction equipment is appropriate?
Next Question
For the buyout verification pass at the clinic oxygen-storage pad, the cricket infill zone measures 5865 SF before a 5% waste allowance. Each insulation board covers 32 SF. How many boards should be ordered?