For the subcontractor quantity check at the bank drive-through canopy, the #6 grade-beam bars takeoff has 87 bars at 24 ft each. Using 1.502 lb per ft for beam reinforcement, what reinforcing weight is estimated?
Correct Answer
C) 3,136 lb
Reinforcing weight equals bar count times length times pounds per foot.
Why This Is the Correct Answer
Reinforcing weight equals bar count times length times pounds per foot.
Why the Other Options Are Wrong
Option A: 2,088 lb
2,088 lb is below the supported result for #6 grade-beam bars; it likely uses the wrong base, period, or account bucket.
Option B: 131 lb
131 lb is below the supported result for #6 grade-beam bars; it likely uses the wrong base, period, or account bucket.
Option D: 3,512 lb
3,512 lb is above the supported result for #6 grade-beam bars; it likely adds an unsupported amount or compares the wrong financial base.
Memory Technique
# Grade-Beam Bars drawer for Concrete Estimator: label reinforcing before counting dollars.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Reinforcing steel; beam bar weight; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
For the subcontractor quantity check at the police evidence-processing room, the patio paving area for paver units is 1785 SF, with 12% attic stock and waste. A carton covers 18 SF. How many cartons should be ordered?
Next Question
For the material-order review at the industrial mezzanine landing, the subgrade stabilization area for geotextile fabric covers 31550 SF, with 5% added for laps and cuts. Each roll covers 1350 SF. How many rolls are needed?