For the buyout verification pass at the radiology equipment platform, a paint crew must complete 10300 SF of block-filler wall area. If planned production is 5100 SF per day, how many whole work days should be scheduled?
Correct Answer
A) 3 work days
Crew days equal quantity divided by daily production, rounded up to whole days.
Why This Is the Correct Answer
Crew days equal quantity divided by daily production, rounded up to whole days.
Why the Other Options Are Wrong
Option B: 2 work days
2 work days is below the supported result for block-filler wall area productivity; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 5 work days
5 work days is above the supported result for block-filler wall area productivity; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 4 work days
4 work days is above the supported result for block-filler wall area productivity; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Block-Filler cart for Superintendent Schedules: crew first, divided second, whole days last.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Finishes; paint crew production planning; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The field condition is: the work should be released only if the team addresses that adhesive anchors rely on bond to concrete. Which hole preparation best matches the condition?
Next Question
The construction team is coordinating a method decision because the controlling field constraint is that substrate movement must be honored. Which tile joint detail is best?