Before releasing the work, the team identifies this condition: water collected by flashing must drain out. Which cavity-wall accessory fits best?
Correct Answer
D) weep openings at flashing
weep openings at flashing best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
weep openings at flashing best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option A: continuous bed-joint reinforcement
continuous bed-joint reinforcement addresses a neighboring field issue, but not the condition or method control required for masonry cavity drainage.
Option B: mortar droppings in cavity
mortar droppings in cavity addresses a neighboring field issue, but not the condition or method control required for masonry cavity drainage.
Option C: rigid insulation blocking the exit
rigid insulation blocking the exit addresses a neighboring field issue, but not the condition or method control required for masonry cavity drainage.
Memory Technique
Condition is the clue; wall is the method check for Foreman Selecting.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Masonry wall methods; flashing and drainage coordination; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The work plan must account for this condition: frame must remain stable during erection. Which steel erection control is most suitable?
Next Question
In the look-ahead meeting, the constraint is that the controlling field constraint is that materials must move without damaging work or access. Which logistics method should the project team carry?