Which multifamily projects fall inside the 60-business-day limit in s. 553.792(1)(a)4?

Correct Answer

A) Those not exceeding 50 units

Section 553.792(1)(a)4 covers "multifamily residential, not exceeding 50 units; site-plan approvals and subdivision plats not requiring public hearing or public notice; and lot grading and site alteration" at 60 business days. A plat that does require a public hearing is outside the paragraph, and so is a larger multifamily project.

Answer Options
A
Those not exceeding 50 units
B
Those of any size
C
Those not exceeding 25 units
D
Those under 100,000 square feet

Why This Is the Correct Answer

Section 553.792(1)(a)4 covers "multifamily residential, not exceeding 50 units; site-plan approvals and subdivision plats not requiring public hearing or public notice; and lot grading and site alteration" at 60 business days. A plat that does require a public hearing is outside the paragraph, and so is a larger multifamily project.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.