An owner records a conditional payment bond and believes the property is now shielded from construction liens. Is it?
Correct Answer
A) No, the property is not exempt from liens filed under part I
Section 713.245(3) states that the owner's property is not exempt from liens filed under part I, and that all lienors must comply with the part to preserve and perfect their lien rights. That is the trade-off for a bond whose coverage is limited to what the contractor has been paid.
Why This Is the Correct Answer
Section 713.245(3) states that the owner's property is not exempt from liens filed under part I, and that all lienors must comply with the part to preserve and perfect their lien rights. That is the trade-off for a bond whose coverage is limited to what the contractor has been paid.
Why the Other Options Are Wrong
Option B: Yes, a recorded bond transfers all lien claims onto the bond itself
Recording does not transfer lien claims onto the bond.
Option C: No, unless the bond amount equals the full contract price
Bond amount does not make the property exempt.
Option D: Yes, as to lienors not in privity with the contractor
All lienors keep their rights under part I.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Contract Admin Questions
A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?
A court enforces a lien against the improvement alone rather than the land. What may it order?
A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?
Who can compel a local government to create a residential master building permit program?
Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?
A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?
What must accompany a bid for construction on a Florida public project under s. 489.131(2)?
A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?
For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?
Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
An owner properly records a Florida notice of contest under section 713.22(2), and the clerk completes the required service and certification. The lienor does not sue within the applicable 60-day period. What further act is required for this lien to be extinguished?
Next Question
Under section 553.792(1)(a)5, what is the maximum unit count in the multifamily category with a 60-business-day decision timeframe for a complete and sufficient application using a local government plans reviewer, absent written waiver?
