What three components make up the amount of a lien transfer deposit or bond?
Correct Answer
C) The amount demanded, 3 years of interest and a fee and cost allowance
Section 713.24(1) sets the amount at the sum demanded in the claim of lien, plus interest on it at the legal rate for 3 years, plus $5,000 or 25 percent of the amount demanded, whichever is greater, to apply to attorney fees and court costs taxed in a proceeding to enforce the lien.
Why This Is the Correct Answer
Section 713.24(1) sets the amount at the sum demanded in the claim of lien, plus interest on it at the legal rate for 3 years, plus $5,000 or 25 percent of the amount demanded, whichever is greater, to apply to attorney fees and court costs taxed in a proceeding to enforce the lien.
Why the Other Options Are Wrong
Option A: The amount demanded, 1 year of interest, and a fee and cost allowance
Interest is for 3 years, not 1.
Option B: The contract price, 3 years of interest, and a fee and cost allowance
The base is the amount demanded, not the contract price.
Option D: The amount demanded and a fee allowance, with no interest component
The amount includes 3 years of interest.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Contract Admin Questions
A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?
A court enforces a lien against the improvement alone rather than the land. What may it order?
A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?
Who can compel a local government to create a residential master building permit program?
Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?
A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?
What must accompany a bid for construction on a Florida public project under s. 489.131(2)?
A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?
For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?
Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A long-lead equipment vendor requires a 30% deposit on a $74,000 package. What cash requirement should be forecast?
Next Question
A glass supplier’s offer states that its price expires five days before the expected award. No extension or price commitment has been agreed. What should the estimator do before submitting the bid?
