EstatePass
Contract AdminContractshard40% of exam part

An interested party files a complaint and the clerk issues a summons to the lienor to show cause. How long does the lienor have?

Correct Answer

D) 20 days after service of the summons

Section 713.21(4) has the clerk issue a summons requiring the lienor to show cause within 20 days after service why the lien should not be enforced by action or vacated and canceled of record. This is a different and shorter clock than the 60-day notice of contest under s. 713.22(2).

Answer Options
A
30 days after service of the summons
B
60 days after service of the summons
C
10 days after service of the summons
D
20 days after service of the summons

Why This Is the Correct Answer

Section 713.21(4) has the clerk issue a summons requiring the lienor to show cause within 20 days after service why the lien should not be enforced by action or vacated and canceled of record. This is a different and shorter clock than the 60-day notice of contest under s. 713.22(2).

Why the Other Options Are Wrong

Option A: 30 days after service of the summons

The period is 20 days, not 30.

Option B: 60 days after service of the summons

60 days is the notice of contest period.

Option C: 10 days after service of the summons

The period is 20 days, not 10.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Contract Admin Questions

A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?

A court enforces a lien against the improvement alone rather than the land. What may it order?

A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?

Who can compel a local government to create a residential master building permit program?

Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?

A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?

What must accompany a bid for construction on a Florida public project under s. 489.131(2)?

A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?

For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?

Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.