A contractor sues a local government to recover amounts due under the Local Government Prompt Payment Act and wins. What does the court award beyond the amount due?
Correct Answer
D) Court costs and reasonable attorney's fees, including on appeal
Section 218.76(3) directs that in an action to recover amounts due under this part the court shall award court costs and reasonable attorney's fees, including fees incurred through appeal, to the prevailing party. The provision runs both ways, so a contractor who loses may owe the entity's fees.
Why This Is the Correct Answer
Section 218.76(3) directs that in an action to recover amounts due under this part the court shall award court costs and reasonable attorney's fees, including fees incurred through appeal, to the prevailing party. The provision runs both ways, so a contractor who loses may owe the entity's fees.
Why the Other Options Are Wrong
Option A: Court costs and attorney's fees at the trial level only
Fees include those incurred through appeal.
Option B: Court costs only, with each party bearing its own fees
The court shall also award reasonable attorney's fees.
Option C: Court costs and attorney's fees capped at 15 percent of the award
The statute sets no 15 percent cap.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Contract Admin Questions
A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?
A court enforces a lien against the improvement alone rather than the land. What may it order?
A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?
Who can compel a local government to create a residential master building permit program?
Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?
A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?
What must accompany a bid for construction on a Florida public project under s. 489.131(2)?
A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?
For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?
Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A pad needs 2,640 compacted cy. Each loose cubic yard yields 0.90 compacted cy. If material is purchased in whole loose cubic yards, what minimum quantity meets the requirement?
Next Question
A trade plans hot work in an occupied renovation area. What should the GC coordinate operationally?
