A contractor sues a local government to recover amounts due under the Local Government Prompt Payment Act and wins. What does the court award beyond the amount due?

Correct Answer

D) Court costs and reasonable attorney's fees, including on appeal

Section 218.76(3) directs that in an action to recover amounts due under this part the court shall award court costs and reasonable attorney's fees, including fees incurred through appeal, to the prevailing party. The provision runs both ways, so a contractor who loses may owe the entity's fees.

Answer Options
A
Court costs and attorney's fees at the trial level only
B
Court costs only, with each party bearing its own fees
C
Court costs and attorney's fees capped at 15 percent of the award
D
Court costs and reasonable attorney's fees, including on appeal

Why This Is the Correct Answer

Section 218.76(3) directs that in an action to recover amounts due under this part the court shall award court costs and reasonable attorney's fees, including fees incurred through appeal, to the prevailing party. The provision runs both ways, so a contractor who loses may owe the entity's fees.

Why the Other Options Are Wrong

Option A: Court costs and attorney's fees at the trial level only

Fees include those incurred through appeal.

Option B: Court costs only, with each party bearing its own fees

The court shall also award reasonable attorney's fees.

Option C: Court costs and attorney's fees capped at 15 percent of the award

The statute sets no 15 percent cap.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Contract Admin Questions

A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?

A court enforces a lien against the improvement alone rather than the land. What may it order?

A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?

Who can compel a local government to create a residential master building permit program?

Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?

A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?

What must accompany a bid for construction on a Florida public project under s. 489.131(2)?

A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?

For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?

Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.