The notice of commencement and permit application name different contractors. What should be corrected?
Correct Answer
C) Correct notice identity data
Chapter 713 requires key notice and permit data consistency.
Why This Is the Correct Answer
Chapter 713 requires key notice and permit data consistency.
Why the Other Options Are Wrong
Option A: The unit-price worksheet
The unit-price worksheet belongs to a different file or record trail; it does not prove the notice identity event.
Option B: The manpower count
The manpower count belongs to a different file or record trail; it does not prove the notice identity event.
Option D: The furniture schedule
The furniture schedule belongs to a different file or record trail; it does not prove the notice identity event.
Memory Technique
File Permit File where the next reviewer would look first.
Reference Hint
Open-book path: tab Florida Statutes Chapter 713 to Sections 713.13 and 713.135 notice information; check the math, FL authority, inspection point, or field record before choosing.
More Contract Admin Questions
When must a signal person be provided during a crane lift under subpart CC?
How may a signal person’s qualification be established under subpart CC?
What does subpart CC require to be carried on crane equipment itself?
A competent person’s excavation inspection finds evidence of a possible cave-in. What does s. 1926.651(k)(2) require?
What does a "permit application" comprise where a private provider has done the plan review?
A tenant asks the general contractor to begin demolition inside an existing space before the permit is issued. What does s. 553.79(1)(a) provide?
The enforcing agency determines that permitted work is not in conformity with the Florida Building Code. What may it do under s. 553.79(1)(a)?
A permit is denied because the plans are found not to comply. What must the local enforcing agency give the applicant?
What must a request for a certificate of occupancy include on a private provider job?
A rejected payment application is corrected and resubmitted to a city whose charter requires the commission to approve payments. When must the city pay or reject it?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass