For a Florida project where a notice of commencement is required, what is the practical permit-step concern before inspection activity proceeds?
Correct Answer
B) Make sure the notice is recorded and posted as required for the permitted work
Florida construction lien and permit procedures tie the notice of commencement to the permitted improvement and inspection process.
Why This Is the Correct Answer
Florida construction lien and permit procedures tie the notice of commencement to the permitted improvement and inspection process.
Why the Other Options Are Wrong
Option A: Treat the bid bond and subcontractor prequalification packet as if they satisfy public notice recording duties
Treat the bid bond and subcontractor prequalification packet as if they satisfy public notice recording duties skips the written authority, scope, price, notice, or release control needed for notice of commencement.
Option C: Wait until final payment to record any project notice
Wait until final payment to record any project notice skips the written authority, scope, price, notice, or release control needed for notice of commencement.
Option D: Ask the subcontractor supplier to record it after closeout
Ask the subcontractor supplier to record it after closeout skips the written authority, scope, price, notice, or release control needed for notice of commencement.
Memory Technique
When construction clashes with lien, let the contract speak before Prepares Permit.
Reference Hint
Open-book path: tab Florida Statutes Chapter 713 to §713.13 Notice of commencement; §713.135 Notice of commencement and building permits; match the project role and timing before choosing.
More Contract Admin Questions
When must a signal person be provided during a crane lift under subpart CC?
How may a signal person’s qualification be established under subpart CC?
What does subpart CC require to be carried on crane equipment itself?
A competent person’s excavation inspection finds evidence of a possible cave-in. What does s. 1926.651(k)(2) require?
What does a "permit application" comprise where a private provider has done the plan review?
A tenant asks the general contractor to begin demolition inside an existing space before the permit is issued. What does s. 553.79(1)(a) provide?
The enforcing agency determines that permitted work is not in conformity with the Florida Building Code. What may it do under s. 553.79(1)(a)?
A permit is denied because the plans are found not to comply. What must the local enforcing agency give the applicant?
What must a request for a certificate of occupancy include on a private provider job?
A rejected payment application is corrected and resubmitted to a city whose charter requires the commission to approve payments. When must the city pay or reject it?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass