A demolition scope is expected to fill eight 30-cy containers. Pull and disposal cost is $725 per container plus $1,050 for loading equipment. What total should be carried?
Correct Answer
B) $6,850
Multiply container count by unit cost and add equipment cost.
Why This Is the Correct Answer
Multiply container count by unit cost and add equipment cost.
Why the Other Options Are Wrong
Option A: $5,800
$5,800 is below the supported result for waste disposal estimate; it likely omits allowance, conversion, coverage, or final round-up.
Option C: $6,525
$6,525 is below the supported result for waste disposal estimate; it likely omits allowance, conversion, coverage, or final round-up.
Option D: $7,900
$7,900 is above the supported result for waste disposal estimate; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Retail Renovation takeoff: count the condition before counting the package.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Demolition estimating; disposal and loading costs; confirm the required quantity, authority, timing, or record before selecting the answer.
More Contract Admin Questions
When must a signal person be provided during a crane lift under subpart CC?
How may a signal person’s qualification be established under subpart CC?
What does subpart CC require to be carried on crane equipment itself?
A competent person’s excavation inspection finds evidence of a possible cave-in. What does s. 1926.651(k)(2) require?
What does a "permit application" comprise where a private provider has done the plan review?
A tenant asks the general contractor to begin demolition inside an existing space before the permit is issued. What does s. 553.79(1)(a) provide?
The enforcing agency determines that permitted work is not in conformity with the Florida Building Code. What may it do under s. 553.79(1)(a)?
A permit is denied because the plans are found not to comply. What must the local enforcing agency give the applicant?
What must a request for a certificate of occupancy include on a private provider job?
A rejected payment application is corrected and resubmitted to a city whose charter requires the commission to approve payments. When must the city pay or reject it?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
