A demolition scope is expected to fill eight 30-cy containers. Pull and disposal cost is $725 per container plus $1,050 for loading equipment. What total should be carried?

Correct Answer

B) $6,850

Multiply container count by unit cost and add equipment cost.

Answer Options
A
$5,800
B
$6,850
C
$6,525
D
$7,900

Why This Is the Correct Answer

Multiply container count by unit cost and add equipment cost.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.