Why must deck attachment changes be coordinated before installation?
Correct Answer
A) Attachment changes can affect diaphragm or deck performance shown in the design
Deck attachment is tied to design performance; changes require coordination and approval.
Why This Is the Correct Answer
Deck attachment is tied to design performance; changes require coordination and approval.
Why the Other Options Are Wrong
Option B: Use metal deck diaphragm coordination to only change the deck color
The trap in B is They only change the deck color. That selection is wrong because it leaves the work at an informal or incomplete stage, while Metal deck diaphragm coordination requires Attachment changes can affect diaphragm or deck performance shown in the design; Deck attachment changes can affect design performance.
Option C: Use metal deck diaphragm coordination to eliminate concrete finishing
Choice C gives They eliminate concrete finishing. Its specific error: it removes the controlling Metal deck diaphragm coordination requirement instead of meeting it.
Option D: Use metal deck diaphragm coordination to replace the need for structural drawings
Choice D (They replace the need for structural drawings) is rejected because it treats Metal deck diaphragm coordination as optional.
Memory Technique
Attach metal deck diaphragm coordination to a checkpoint: remember the function, then the wording Attachment changes can affect diaphragm or deck performance shown in the design.
Reference Hint
Open Steel Construction Manual, 15th Ed.; Steel Deck Institute and Steel Joist Institute standard practice; use the index entry or section for "Deck diaphragm coordination" to confirm that Deck attachment is tied to design performance; changes require coordination and approval.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contract clause is applied to this fact pattern: which review asks whether the bidder has capacity, experience, resources, and integrity to perform?
Next Question
For a 6000 psi concrete mixture, the superintendent checks the low-test limit in the ACI acceptance criteria. Ignoring the three-test average for a moment, which individual test value is the minimum allowed by that branch?