Wall sheathing nailing is visibly wider than the approved fastening schedule. What should happen?
Correct Answer
B) Correct fastening to the approved schedule before cover or inspection acceptance
Sheathing fastening affects structural performance and should match the approved schedule before cover.
Why This Is the Correct Answer
Sheathing fastening affects structural performance and should match the approved schedule before cover.
Why the Other Options Are Wrong
Option A: The framing crew should paint nail heads
Choice A gives Paint nail heads. Its specific error: the option shifts to a different trade task; the tested Sheathing fastening correction function or field correction is Correct fastening to the approved schedule before cover or inspection acceptance.
Option C: The framing crew should wait for drywall
In wood framing, Wait for drywall is the wrong selection for Sheathing fastening correction: the action skips the timing, documentation, or field-control step needed for Sheathing fastening correction.
Option D: The framing crew should ignore edge spacing
The trap in D is Ignore edge spacing. That selection is wrong because it tries to bypass the Sheathing fastening correction checkpoint.
Memory Technique
Remember sheathing fastening correction by its jobsite consequence: the correct move points to Correct fastening to the approved schedule before cover or inspection acceptance.
Reference Hint
Open International Building Code wood construction provisions; APA and truss handling practice; use the index entry or section for "Wood sheathing fastening" to confirm that Sheathing fastening affects structural performance and should match the approved schedule before cover.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass