Before concrete is placed on composite metal deck, which deck condition must be verified?
Correct Answer
A) Required deck fastening and side-lap attachment are complete
Metal deck must be fastened and side laps attached as detailed before it is loaded with concrete. Paint, manuals, or glazing do not establish deck diaphragm or placement readiness.
Why This Is the Correct Answer
Metal deck must be fastened and side laps attached as detailed before it is loaded with concrete. Paint, manuals, or glazing do not establish deck diaphragm or placement readiness.
Why the Other Options Are Wrong
Option B: Only final field paint is complete
Choice B (Final field paint only is complete) is rejected because it leaves the work at an informal or incomplete stage, while Steel deck fastening before concrete requires Required deck fastening and side-lap attachment are complete.
Option C: Begin fastening deck after O&M manuals are submitted
In metals work, O&M manuals are submitted is the wrong selection for Steel deck fastening before concrete: the choice would not get the project to Required deck fastening and side-lap attachment are complete, which is the Steel deck fastening before concrete result verified by the source.
Option D: Wait for window glazing before fastening composite deck
The trap in D is Window glazing is installed. That selection is wrong because the option shifts to a different trade task; the tested Steel deck fastening before concrete function or field correction is Required deck fastening and side-lap attachment are complete; Metal deck fastening and side-lap attachment are verified before concrete placement.
Memory Technique
File steel deck fastening before concrete under a switch: condition first, number or duty second, answer Required deck fastening and side-lap attachment are complete.
Reference Hint
Open Steel Construction Manual, 15th Ed.; Steel Deck Institute and Steel Joist Institute standard practice; use the index entry or section for "SDI metal deck installation and concrete placement readiness" to confirm that Metal deck must be fastened and side laps attached as detailed before it is loaded with concrete.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Random cracks appeared on yesterday's slab panel before the sawcut crew arrived. For the next panel, how should contraction-joint timing be controlled?
Next Question
An acoustical ceiling grid layout leaves a 2 in. sliver tile along one wall of a conference room. The reflected ceiling plan does not require that condition. What should be done before installation proceeds?