NASCLAMetalsmedium5% of exam part

Before concrete is placed on composite metal deck, which deck condition must be verified?

Correct Answer

A) Required deck fastening and side-lap attachment are complete

Metal deck must be fastened and side laps attached as detailed before it is loaded with concrete. Paint, manuals, or glazing do not establish deck diaphragm or placement readiness.

Answer Options
A
Required deck fastening and side-lap attachment are complete
B
Only final field paint is complete
C
Begin fastening deck after O&M manuals are submitted
D
Wait for window glazing before fastening composite deck

Why This Is the Correct Answer

Metal deck must be fastened and side laps attached as detailed before it is loaded with concrete. Paint, manuals, or glazing do not establish deck diaphragm or placement readiness.

Why the Other Options Are Wrong

Option B: Only final field paint is complete

Choice B (Final field paint only is complete) is rejected because it leaves the work at an informal or incomplete stage, while Steel deck fastening before concrete requires Required deck fastening and side-lap attachment are complete.

Option C: Begin fastening deck after O&M manuals are submitted

In metals work, O&M manuals are submitted is the wrong selection for Steel deck fastening before concrete: the choice would not get the project to Required deck fastening and side-lap attachment are complete, which is the Steel deck fastening before concrete result verified by the source.

Option D: Wait for window glazing before fastening composite deck

The trap in D is Window glazing is installed. That selection is wrong because the option shifts to a different trade task; the tested Steel deck fastening before concrete function or field correction is Required deck fastening and side-lap attachment are complete; Metal deck fastening and side-lap attachment are verified before concrete placement.

Memory Technique

File steel deck fastening before concrete under a switch: condition first, number or duty second, answer Required deck fastening and side-lap attachment are complete.

Reference Hint

Open Steel Construction Manual, 15th Ed.; Steel Deck Institute and Steel Joist Institute standard practice; use the index entry or section for "SDI metal deck installation and concrete placement readiness" to confirm that Metal deck must be fastened and side laps attached as detailed before it is loaded with concrete.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.