Before concrete is placed on composite metal deck, which deck condition must be verified?
Correct Answer
A) Required deck fastening and side-lap attachment are complete
Metal deck must be fastened and side laps attached as detailed before it is loaded with concrete. Paint, manuals, or glazing do not establish deck diaphragm or placement readiness.
Why This Is the Correct Answer
Metal deck must be fastened and side laps attached as detailed before it is loaded with concrete. Paint, manuals, or glazing do not establish deck diaphragm or placement readiness.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Random cracks appeared on yesterday's slab panel before the sawcut crew arrived. For the next panel, how should contraction-joint timing be controlled?
Next Question
An acoustical ceiling grid layout leaves a 2 in. sliver tile along one wall of a conference room. The reflected ceiling plan does not require that condition. What should be done before installation proceeds?
