Random cracks appeared on yesterday's slab panel before the sawcut crew arrived. For the next panel, how should contraction-joint timing be controlled?
Correct Answer
D) Saw as soon as the concrete can support cutting without raveling, within the specified early-cut window
Contraction joints need to be cut early enough to create a weakened plane before random shrinkage cracking, but not so early that edges ravel. Other choices: waiting days, waiting until curing ends, or omitting joints allows uncontrolled cracking.
Why This Is the Correct Answer
Contraction joints need to be cut early enough to create a weakened plane before random shrinkage cracking, but not so early that edges ravel.
Why the Other Options Are Wrong
Option A: The crew should wait at least two days so the concrete reaches more strength
Choice A gives Wait at least two days so the concrete reaches more strength. Its specific error: it leaves the work at an informal or incomplete stage, while Sawcut timing requires Saw as soon as the concrete can support cutting without raveling, within the specified early-cut.
Option B: The crew should cut only after all curing is complete
Choice B (Cut only after all curing is complete) is rejected because the option delays or omits the controlling step.
Option C: Skip joints because random cracks already relieved the stress
In concrete work, Skip joints because random cracks already relieved the stress is the wrong selection for Sawcut timing: the action skips the timing, documentation, or field-control step needed for Sawcut timing.
Memory Technique
Tag the scene with sawcut timing: wrong actor or wrong timing means the fix is not Saw as soon as the concrete can support cutting without raveling, within the specified early-cut window.
Reference Hint
Open The Contractor's Guide to Quality Concrete Construction, 4th Ed., 2018; use the index entry or section for "Slab contraction joint timing" to confirm that Contraction joints need to be cut early enough to create a weakened plane before random shrinkage cracking, but not so early that edges ravel.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
