A continuous steel shelf angle passes through exterior insulation and creates a cold line on the interior finish. What building-science term describes that condition?
Correct Answer
B) Thermal bridge
A thermal bridge is a conductive path through insulation that increases heat flow and can create cold surface temperatures. Other choices describe liquid moisture movement, vapor control, or roof drainage.
Why This Is the Correct Answer
A thermal bridge is a conductive path through insulation that increases heat flow and can create cold surface temperatures. Other choices describe liquid moisture movement, vapor control, or roof drainage.
Why the Other Options Are Wrong
Option A: Capillary rise
Choice A (Capillary rise) is rejected because the option does not produce the required Thermal bridge outcome, Thermal bridge.
Option C: Vapor diffusion retarder
The trap in C is Vapor diffusion retarder. That selection is wrong because it answers the Thermal bridge prompt with the wrong practical move.
Option D: Positive drainage
Choice D gives Positive drainage. Its specific error: it leaves out the controlling Thermal bridge result: Thermal bridge.
Memory Technique
Attach thermal bridge to a fastener row: remember the function, then the wording Thermal bridge.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Building enclosure thermal-control concepts" to confirm that A thermal bridge is a conductive path through insulation that increases heat flow and can create cold surface temperatures.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass