Force-account work means the changed work is typically priced from:
Correct Answer
D) Actual documented labor, material, equipment, and subcontractor cost records
Force-account work is priced from documented actual costs such as labor, material, equipment, and subcontractor records. Other choices do not establish changed-work cost.
Why This Is the Correct Answer
Force-account work is priced from documented actual costs such as labor, material, equipment, and subcontractor records. Other choices do not establish changed-work cost.
Why the Other Options Are Wrong
Option A: The color of the field report
Choice A gives The color of the field report. Its specific error: it leaves out the controlling Force account result: Actual documented.
Option B: Base the force account response on the owner's move-in announcement
Choice B (The owner's move-in announcement only) is rejected because the action skips the timing, documentation, or field-control step needed for Force account.
Option C: Classify the condition as a deleted addendum
In procurement and contracting, A deleted addendum is the wrong selection for Force account: it removes the controlling Force account requirement instead of meeting it.
Memory Technique
Use force account as the label and Actual documented labor, material, equipment, and subcontractor cost records as the definition to recall under pressure.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Force-account concept" to confirm that Force-account work is priced from documented actual costs such as labor, material, equipment, and subcontractor records.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass