Runoff has cut under a silt fence after a storm. What maintenance is needed?
Correct Answer
A) Rekey or repair the fence, remove sediment as required, and restore grade around it.
Undermined silt fence no longer controls sheet flow and needs repair.
Why This Is the Correct Answer
Undermined silt fence no longer controls sheet flow and needs repair.
Why the Other Options Are Wrong
Option B: Add more water upstream
In site construction, Add more water upstream. is the wrong selection for Silt fence undermined: the choice would not get the project to Rekey or repair the fence, remove sediment as required, and restore grade around it.
Option C: The site crew should leave the gap for drainage
The trap in C is Leave the gap for drainage. That selection is wrong because the option does not produce the required Silt fence undermined outcome, Rekey or repair the fence, remove sediment as required, and restore grade around it.
Option D: The site crew should move spoil onto the fence, leaving silt fence undermined unverified
Choice D gives Move spoil onto the fence. Its specific error: it points to Move spoil onto the fence. but.
Memory Technique
Tag the scene with silt fence undermined: wrong actor or wrong timing means the fix is not Rekey or repair the fence, remove sediment as required, and restore grade around it.
Reference Hint
Open Developing Your Stormwater Pollution Prevention Plan, EPA 833-R-06-004, 2007; use the index entry or section for "EPA 833-R-06-004 - SWPPP development / permit and inspection topics" to confirm that Undermined silt fence no longer controls sheet flow and needs repair.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass