When must an excavation atmosphere be tested?
Correct Answer
A) Before entry where oxygen deficiency or hazardous atmosphere could reasonably be expected.
OSHA requires testing where hazardous atmospheres could reasonably exist, such as near landfills or hazardous substances.
Why This Is the Correct Answer
OSHA requires testing where hazardous atmospheres could reasonably exist, such as near landfills or hazardous substances.
Why the Other Options Are Wrong
Option B: Test only after backfill is complete
Choice B (Only after backfill) is rejected because it leaves the work at an informal or incomplete stage, while Hazardous atmosphere excavation requires Before entry where oxygen deficiency or hazardous atmosphere could reasonably be expected.
Option C: Record only a midday air reading
In site construction, Only at lunch is the wrong selection for Hazardous atmosphere excavation: the option delays or omits the controlling step.
Option D: Assume excavation atmospheres never require testing on construction sites
The trap in D is Never in construction excavations. That selection is wrong because the choice would not get the project to Before entry where oxygen deficiency or hazardous atmosphere could reasonably be expected.
Memory Technique
Link hazardous atmosphere excavation to its book condition; a different condition means a different answer than Before entry where oxygen deficiency or hazardous atmosphere could reasonably be expected.
Reference Hint
Open OSHA 29 CFR 1926 Subpart P; EPA Construction General Permit concepts where applicable; use OSHA 1926.651(g) to confirm that OSHA requires testing where hazardous atmospheres could reasonably exist, such as near landfills or hazardous substances.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A floor under construction has 7,800 sf of protected building area. Using one 2A extinguisher per 3,000 sf or major fraction, how many extinguishers are required before travel-distance checks?
Next Question
At the preinstallation conference, what supports payment for stored materials?
