After the revised drawing is issued, where should silt fence normally be placed?
Correct Answer
C) Downslope of disturbed soil before sediment leaves the site
Downslope of disturbed soil before sediment leaves the site is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 85.
Why This Is the Correct Answer
Downslope of disturbed soil before sediment leaves the site is the controlling requirement
Why the Other Options Are Wrong
Option A: Base the silt fence response on across active vehicle gates only
Choice A gives Across active vehicle gates only. Its specific error: the action skips the timing, documentation, or field-control step needed for Silt fence.
Option B: Select inside finished rooms for silt fence
Choice B (Inside finished rooms) is rejected because it leaves out the controlling Silt fence result.
Option D: Use at roof drains as the stated limit in silt fence
The trap in D is At roof drains only. That selection is wrong because the option delays or omits the controlling step.
Memory Technique
File silt fence under a pay line: condition first, number or duty second, answer Downslope of disturbed soil before sediment leaves the site.
Reference Hint
Open Developing Your Stormwater Pollution Prevention Plan, EPA 833-R-06-004; use the index entry or section for "Sediment barrier placement" to confirm that Downslope of disturbed soil before sediment leaves the site is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass